A finishes the job at standard rate in 12 days.
So in 1 day, the part of job done by A = 1/12
Similarly the part of job done by B in 1 day

So, in (2 alternate days work of 'A' and 'B')
3 x 4 = 12 days
They will finish 3 x (5/18) = 15/18 th of the work.
Work remaining = 1 - (15/18) = 3/18 = 1/6
This is finished by A alone in = 2 days.
Hence, total number days = 12 + 2 = 14 days
Cancel reply

Your email address will not be published. Required fields are marked *


Cancel reply

Your email address will not be published. Required fields are marked *

Why Practice with Avatto?

High Quality MCQsExam-focused questions with accurate answers
Detailed ExplanationsStep-by-step explanations to enhance learning
Latest Exam PatternBased on updated syllabus and pattern
Performance AnalyticsTrack performance and improve weak areas
100% Free PracticePractice unlimited questions for free