UGC NET Management Previous Year Solved Papers - December 2018

36. Match the items of List-I with the items of List-II and choose the correct answer from the code given below.

List-IList-II
(a)X chart(i) Number of defects
(b) P chart(ii) Variations between samples
(c) C chart(iii) Variations within samples
(d) R chart(iv) Proportion of defectives

Cancel reply

Your email address will not be published. Required fields are marked *


Cancel reply

Your email address will not be published. Required fields are marked *


37. Which among the following concepts is not related to product design?

Cancel reply

Your email address will not be published. Required fields are marked *


Cancel reply

Your email address will not be published. Required fields are marked *


38.

Arrange the operations in production planning and control in correct sequence:
(i) Routing
(ii) Dispatching
(iii) Follow up
(iv) Scheduling
Choose the correct answer from the code given below:

  • Option :
  • Explanation : NO OPTION IS CORRECT
Cancel reply

Your email address will not be published. Required fields are marked *


Cancel reply

Your email address will not be published. Required fields are marked *


39. The following statements relate to the project network. Choose the correct code for the statements being correct or incorrect.
Statement I: An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.
Statement II: The activities in a critical path can be preponed or postponed.
Code:

Cancel reply

Your email address will not be published. Required fields are marked *


Cancel reply

Your email address will not be published. Required fields are marked *


40. Match the items of List-I with the items of List-II and choose the correct answer from the code given below.

List-IList-II
(a) Cycle stock(i) Hedge against the possibility of stockout
(b) Transit stock(ii) Stock to meet inventory cycle
(c) Buffer stock(iii) The stock moved between various elements of the supply chain
(d) Safety stock(iv) Extra stock to meet fluctuations in demand

Cancel reply

Your email address will not be published. Required fields are marked *


Cancel reply

Your email address will not be published. Required fields are marked *


Related Quiz.
December 2018