0. The following statements relate to the project network. Choose the correct code for the statements being correct or incorrect. Statement I: An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities. Statement II: The activities in a critical path can be preponed or postponed.Code:
Both the statements I and II are correct.
Both the statements I and II are incorrect.
Statement II is correct, but I is incorrect.
Statement I is correct, but II is incorrect.