0. Arrange the operations in production planning and control in correct sequence:(i) Routing(ii) Dispatching(iii) Follow up(iv) SchedulingChoose the correct answer from the code given below:
Arrange the operations in production planning and control in correct sequence:(i) Routing(ii) Dispatching(iii) Follow up(iv) SchedulingChoose the correct answer from the code given below:
(ii), (iv), (iii), (i)
(i), (iv), (ii), (iii)
(iv), (i), (iii), (ii)