July2016 cs Q43

0. Which of the following is not included in waterfall model?

  • Option : B
  • Explanation :
    Waterfall model have following phases:
  • Requirement Analysis
  • System Design
  • Implementation
  • Testing
  • Deployment
  • Maintenence
  • It doesn't include Risk analysis. So, option (B) is correct.