Financial Reporting and Analysis Q78

  • Option : B
  • Explanation : When the outcome can be measured reliably the percentage-ofcompletion method is used. When the outcome cannot be measured reliably the completed contract method is used. The cost recovery method is used for installment sales, not for long- term projects.