Financial Reporting and Analysis Q81

0. Dynamo Construction Company uses the percentage-of-completion method to recognize revenue from its long term construction contracts and estimates percent completion based on expenditures incurred as a percentage of total estimated expenditures. A three- year contract for €15 million was undertaken. The project is now at the end of its second year, and the following end-of-year information is available:
 Year 1 Year 2
Costs incurred during year 4,150,0003,800,000
Estimated total costs  8,500,0008,500,000

  • Option : A
  • Explanation : In year 2, the revenue is: 15 million * 3,800,000 / 8,500,000 = 6,705,882. The profit is: 6,705,882 - 3,800,000 = 2,905,882.