Corporate Finance Q48

0. A project manager is working on a complicated large-scale project for a company that will require multiple investments over time while giving cashinflows in some years over a period of four years. He develops the following cash flow schedule for his project:
Year 0-£900,000.00
Year 1 £6,344,400.00
Year 2- £8,520,364.00
Year 3 £2,245,066.00
Year 4 £650,000.00

  • Option : C
  • Explanation : The question requires that NPV be found at each of the discount rates given as answer choices. When the NPV of cash flows is negative, the project is least likely to be undertaken.
    Using a financial calculator, first enter the cash flows.
    CF0 = - 900,000, CF1 = 6,344,400, CF2 = -8,520,364, CF3 = 2,245,066, CF4 = 650,000
    Then, determine the NPV for each of the given discount rates When I = 13%, CPT NPV = -3,581
    When I = 16%, CPT NPV = +34,600 When I = 18%, CPT NPV = +59,097
    Hence, project will least likely be undertaken when the discount rate is 13% as the NPV is negative, while at the other two discount rates it is positive.
Cancel reply

Your email address will not be published. Required fields are marked *


Cancel reply

Your email address will not be published. Required fields are marked *