Corporate Finance Q65

  • Option : C
  • Explanation : For these projects, a discount rate of 15.09 percent would yield the same NPV for both (an NPV of 11.03). The cross over point needs to be before the lower IRR (21.79).
    Note: The discount rate (crossover point) at which both the projects have the same NPV is the IRR for the differences in cash flows of the projects. For instance, in this case, it is CF0 = 0, CF1 = -22, CF2 = -22, CF3 = -22, CF4 = 88, CPT IRR. IRR = 15.09%.