Nov2017 cs Q49

  • Option : A
  • Explanation :
    First we will make gantt chart of given process then we will calculate turn around time and waiting time of individual process.
    Nov2017 cs
    Now we have to calculate average waiting time for schedule:
    avg waiting time = wt(P1 + P2 + P3 + P4 )/number of process.
    ie. (9 + 0 + 15 + 2) / 4
    = 26 / 4
    = 6.5
    So, option (A) is correct.