Labour Rate of Pay Variance can be calculated by which one of the following equations ?
A. | Budgeted Labour Costs-Actual Labour Costs |
B. | (Standard Hours - Actual Hours) x Actual Wage Rate |
C. | (Standard Wage Rate-Actual Wage Rate) x Actual Hours Worked |
D. | (Standard Wage Rate-Actual Wage Rate) x Standard Hours Worked |
Answer : C Explanation : |
|
Option: A Explanation : Explanation will come here. Explanation will come here. Explanation will come here. Explanation will come here. Explanation will come here. |