June 2015

1: A manufacturing firm has four work stations, A, B, C and'D in series with individual capacity of processing 450, 390, 360 and 400 Uhits per day respecnvelf and tneadual outpuf of the firm is 306 units per day. The system capacity and system efficiency of the-firm shall respectively be :
A.

400 and 100%

B.

450 and 120%

C.

360 and 85%

D.

390 and 95%

 

Answer : C

Explanation :

Write your comments here:


Report Error
 

Option: A

Explanation : Explanation will come here. Explanation will come here. Explanation will come here. Explanation will come here. Explanation will come here.