1:

Let the clock-driven scheme for generating initial sequence numbers is used with a 15-bit wide clock counter. The clock ticks once every 100 msec, and the maximum poacket lifetime is 60 sec. How often need resynchronization take place when the data consumes 240 sequence numbers/min?

A.

3261.3 sec

B.

4261.3 sec

C.

5361.3 sec

D.

6261.3 sec

 

Answer : C

Explanation :

At 240 sequence numbers/min, the actual sequence number = 4t
where t is in sec.
Left edge of the forbidden region
          = 10 (t - 3216.8).
Equating these two formulas, we find that they intersect at t = 5361.3 sec 

Write your comments here:


Report Error
 

Option: A